Troubleshoot Housing Cycle Rollovers
Last updated: October 5, 2026
This guide helps you resolve common issues that occur during housing cycle rollovers. Status indicators in the rollover review table alert you to potential problems before you execute the rollover.
Note: Review the rollover status table carefully before executing rollovers. Green statuses (OK) indicate the rollover will succeed, yellow indicates warnings, and red indicates critical errors that must be resolved first.
Understanding Rollover Statuses
The rollover review table displays separate status columns for different data types. Each status indicates whether that specific element can be rolled over successfully.

Bed/Residency Statuses
OK (green): Bed can be rolled over successfully
Gap in Residency (yellow): Minor date gap between cycles; may proceed with caution
Large Gap in Residency (red): Significant date gap requiring review
Term Overlap (red): Residency dates conflict with existing assignments
Bed Taken (red): Target bed is already assigned to another resident
Residency Ended (red): Source residency has ended and cannot transfer
Residency Canceled (red): Source residency was canceled
Application Statuses
OK (green): Application can be rolled over successfully
No Application (yellow): Resident has no application in the source cycle
Template Mismatch (yellow): Application templates differ between cycles
Already Has Application w/ Residency (yellow): Resident already has an application in target cycle
Meal Plan Statuses
OK (green): Meal plan can be rolled over successfully
Overlapping (yellow): Meal plan dates overlap with existing assignment
DNE in Cycle (yellow): Meal plan isn't enabled in the target cycle
Dates Error (red): Meal plan dates are incompatible
After rollover execution, statuses update to either "Success" (green) or "Failed" (red).
Common Issues and Solutions
Bed Taken
Problem: The bed you're trying to rollover is already assigned to another resident in the target cycle.
Solutions:
Reassign the conflicting resident to a different bed in the target cycle
Cancel the conflicting assignment if it was created in error
Choose a different bed for the resident you're rolling over
Term Overlap
Problem: The residency dates conflict with another assignment in the target cycle.
Solutions:
Review the conflicting residency dates in the target cycle
Adjust or cancel the overlapping assignment
Verify the target cycle dates are configured correctly
Large Gap in Residency
Problem: There's a significant date gap between the source residency end date and target residency start date.
Solutions:
Review whether this gap is expected (e.g., summer break between academic years)
Adjust residency dates in either cycle if the gap is unintentional
Proceed with rollover if the gap is intentional and acceptable
Template Mismatch
Problem: Application or questionnaire templates differ between the source and target cycles.
Solutions:
Use selective rollover to transfer only compatible data (e.g., beds and tags, but not application answers)
Update the target cycle to use the same templates as the source cycle
Have residents complete new applications in the target cycle
Application answers cannot be transferred when templates don't match, as the questions and fields may be different.
DNE in Cycle (Meal Plans)
Problem: The meal plan assigned in the source cycle isn't enabled in the target cycle.
Solutions:
Navigate to Admin > Setup > Cycles > [Target Cycle] > Meal Plans tab
Enable the missing meal plan by checking the box next to it
Ensure the meal plan's availability dates cover the target cycle dates
Save your changes and retry the rollover
Meal plans are created once at the system level (Admin > Setup > Meal > Meal Plans), then enabled per cycle. The rollover matches meal plans by their internal ID, so the same system-level meal plan must be enabled in both cycles.
Residency Canceled or Ended
Problem: The source residency has been canceled or marked as ended.
Solutions:
Verify the residency status is correct—if canceled in error, restore it before rolling over
Exclude these residents from the rollover selection if their status is accurate
Create new residencies manually if these students should be included in the target cycle
Transactions Not Created
Problem: Residencies rolled over successfully but no charges were created in the target cycle.
Solutions:
Use the "Rollover Eligible Residencies With Transactions" bulk action option
Verify automatic charges are configured in the target cycle
Process transactions manually for affected residents if needed
The standard "Rollover Eligible Residencies" option does NOT create transactions. You must explicitly select "With Transactions" to generate charges. We're working on simplifying this in a future update.
Rollover Shows "Failed" Despite Success
Problem: Some rollovers show "Failed" status but the data appears to have transferred correctly.
Solutions:
Refresh the rollover review page to see updated statuses
Check the target cycle to verify if the data actually transferred
If data transferred successfully despite the "Failed" status, no action is needed
Contact support if rollovers genuinely failed and need to be retried
Large Batch Rollovers Stall or Timeout
Problem: Rolling over many residents (100+) causes the process to stall or appear stuck.
Solutions:
Wait for background processing to complete, large batches process asynchronously
Break very large rollovers (500+ residents) into smaller batches
Monitor the progress indicator ("Processed X / Y")
Rollovers with more than 20 residents process in the background. The system will poll for updates, and you can navigate away from the page while processing continues.
No Application to Rollover
Problem: Status shows "No Application" for residents you want to roll over. This issue should not occur, as all residencies MUST be tied to an application and cycle.
Solutions:
Verify these residents actually completed applications in the source cycle
Reach out to support for guidance.
Best Practices to Prevent Issues
Test in sandbox first: Run a test rollover in your sandbox environment to identify configuration problems
Match configurations: Ensure meal plans, application templates, and questionnaires are consistent across cycles before rolling over
Review eligibility: Check all statuses in the review table before executing bulk rollovers
Start small: Test rollover with a small group of residents before processing hundreds
Verify target cycle setup: Confirm the target cycle is fully configured with dates, beds, and required materials
Still Need Help?
If you're experiencing issues not covered here, contact Housing.Cloud support with the following information:
Source and target cycle names
Number of residents affected
Specific error statuses shown
Screenshots of the rollover review table
What rollover options you selected
For step-by-step rollover instructions, see 📄 Complete a Housing Cycle Rollover.